Contracts

Force majeure and hardship

Storms, epidemics, embargoes, soaring raw material prices: when you're excused, when you can renegotiate, and how to write clauses that actually work.

Mr. Dan
Mr. Dan10+ years of export experience

In recent years, epidemics, conflicts and shipping crises have left many companies unable to deliver as contracted. Those with a good force majeure clause were excused; those without one had to pay damages.

What is force majeure?

An objective event that couldn't be foreseen and couldn't be overcome despite taking all necessary measures. Commonly listed examples:

  • Natural disasters: storms, floods, earthquakes, drought, fire.
  • Epidemics and government lockdowns.
  • War, riots, embargoes, widespread strikes.
  • Government decisions banning the export or import of the goods.

How to write a clause that works

  • List the events specifically, followed by "and other similar events".
  • Notice obligation: the affected party must give notice within a set period, for example 7 days, with a certificate from a competent authority such as a chamber of commerce or local government.
  • Consequences: the time for performance is extended accordingly. If the event lasts beyond a set period, for example 60 days, either party may terminate the contract without compensation.
  • Duty to mitigate: both parties must make efforts to limit losses.

Are price changes force majeure?

Usually not. Rising raw material prices and freight rates are business risks. If you're worried, add a hardship clause: when costs rise above a specific threshold, the parties must renegotiate the price. Or use a price adjustment clause tied to a market index for long-term contracts.

Force majeure is interpreted differently in different legal systems. The contract's governing law decides which interpretation applies. So the more specific the clause, the less it depends on how a court or arbitral tribunal reads it.